Current Monthly Report

January - June 2019



January
February
March
April
May
June
Total Permit
Transaction
3934
3867
3893
3909
4225

Total Permit
Fees Collected
$328,880.82
$289,202.79
$260,727.59
$340,315.38
$281,475.26

Single Family
Dwellings
Permitted

460*

139*

119*

382*

102
 

Estimated
Cost of
Construction

$91,994,910.00

$49,670,320.00

$45,191,601.00

$91,193,110.00
 

$40,260,612.00

Commercial
Buildings
Permitted

10

7

 5

8

4

Commercial
Estimated Cost
of Construction
$5,173,197.00
$23,223,805.00
$6,792,854.00
$4,525,392.00
$3,557,569.00


*January 127 SFD + 3&4 family 13 bldg. 50 units + 5 or more family 9 bldg. 283 units= 460
* February 114 SFD + 3&4 family 1 bldg. 4 units+ 5 or more family 4 bldg. 21 units = 139 
* March 96 SFD + 5 or more family 4 bldg. 23 units= 119
* April 124 SFD + 2 family 2 bldg. 4 units + 3&4 family 2 bldg. 8 units + 5 or more family 12 bldg. 246 units= 382

         

July - December 2019



July
August
September
October
November
December
Total Permit
Transactions






Total Permit
Fee Collected






Single Family
Dwellings
Permitted






Estimated Cost
of Construction






Commercial Buildings
Permitted






Commercial Estimated
Cost of Construction






    
*