Road and Bridge Projects
 You are viewing upcoming and active projects. All construction projects require cooperation from the contractor, utility companies, the owner and especially the users (the taxpayers that are paying for the improvement).

 District Project Name (click on project name) Status/Pics Updated
   CURRENT PUBLIC WORKS PROJECTS
(click to view all projects)
  2/8/17

CURRENT PROJECTS-2017
Updated 2/8/17


           

      ROADS

  • Helen McCall Park Connector Road- 60% set of plans have been received and reviewed by staff. Comments have been issued to the engineer.
  • CR 395 & CR 30A Intersection improvements. 60% set of plans have been received and reviewed. Staff has met with the utility companies and have received feedback from the utility companies. Meeting has been scheduled with Okaloosa gas to discuss conflict. Project is still under design.
  • CR 30A Resurfacing Project.  Construction is complete

            State Funded Projects

  • CR 181C-resurfacing of CR 181C from SR 81 to Holmes County Line. This project is funded by the State of Florida Small County Outreach Program in the amount of $2,578,011.00. Contractor is finishing up the punch list items and this project is scheduled to be completed by mid-February 2017.
  • Walton Bridge Road-paving of Walton Bridge Road from south of Doctor’s Road to Rock Hill Road. This project is funded by the State of Florida Small County Outreach Program in the amount of $2,328,126.00. Construction bid has been awarded to Roberts and Roberts Contracting, Inc.. Construction will begin-February 15, 2017.
  • CR 183(Kidd/Line Road)-resurfacing of CR 183 from SR 10 (US 90) to Homes County Line (7.09 miles). This project is funded by the State of Florida Small County Road Assistance Program in the amount of $4,000,005.00. Design has been completed and is currently awaiting permitting.
  • CR 285-resurfacing and reconstruction of CR 285 from SR 187 to the Alabama State Line (3.47 miles). Paving has been completed. Project has been completed.
  • McKinnon Bridge Road- Paving of McKinnon Bridge Road from north of Bruce Creek Relief Bridge to South of Red Hill Road. This project is funded by the State of Florida Small County Outreach program in the amount of $1,078,480.00. Punch list items are being addressed and construction is expected to be completed February 2017.

 

2014/2015 Capital Improvement Projects

  • Fluffy Landing-paving south of old Jolly Bay Road. Crews have cleared and stabilized. Paving has started and will be completed February/March 2017.
  • Shady Lane-paving .24 miles. Crews have cleared and stabilized. Utilities have been relocated. Paving will be completed February/March 2017
  • Paradise Point Lane- paving of Casa Grande Lane to the end. Crews has cleared row and utilities are currently being relocated. Paving has been scheduled March 2017.
  • Casa Grande Lane- paving .1 Losa Roblas Grande to Paradise Pointe Lane. Crews have cleared ROW and utilities are currently being relocated. Paving has been scheduled March 2017.
  • Blue Bell Circle- paving .25 E Mack Bayou to Mack Bayou. Plans have been completed. Crews have cleared and utilities have been relocated. Paving scheduled April/May 2017.
  • Pine Knoll Lane- paving length .1 miles. Task Order has been sent to Genesis Engineering for fee/man hour proposal. Project is currently under design.
  • Oak Hill Lane-paving length .1 miles. Task Order has been sent to Genesis Engineering for fee/man hour proposal. Project is currently under design.
  • Blue Gulf Drive- paving length .1 miles. Task Order has been sent to Genesis Engineering for fee/man hour proposal. Project is currently under design.
  • East Point Washington Road-realignment and paving. Staff has received a consent letter from FDEP in regards to an 60’ easement. Request for Qualification have been received and are currently under review by staff.

BRIDGES/PEDESTRIAN BRIDGES

  • Big Redfish Bridge-replacement of culvert and bridge. This project is funded by State of Florida Hazard Mitigation Grant program in the amount of $603,450.00. Design has been completed and utilities are currently being located. Will advertise for construction bids summer 2017.
  • McKinnon Bridge Road Bridge-replacement of bridge. This project is a Capital Improvement project. Design and mussel study completed. Permits have been received. Utilities are being relocated.
  • Western Lake Pedestrian Bridge Phase I-construction of pedestrian bridge and multi-use path. This project is funded through the State of Florida LAP program in the amount of $1,049,106.00. Design and permitting has been completed. Construction has begun and is expected to be completed February/March 2017.
  • Oyster Lake- Installation of retaining wall and earth blanket. Working on permit modification to address storm damage.

PARKING/MULTI-USE PATHS/SIDEWALKS

  • Western Lake Pedestrian Bridge Phase II-construction of parking spaces, drainage and landscaping improvements within the ROW. Design has been completed and construction is underway. Project is expected to be completed March/April 2017.
  • US 395N (from US 98-Bayou Road)- road construction project is to include the addition of a multi-use path on CR 395 and US 98 to the north end of the road terminating at Choctawhatchee Bay. Project length is 1.4 miles. 30% design submittal has been received and reviewed by staff.
  • S. Holiday Road Sidewalk- this project was approved in the list of 2016 TIFT projects. 90% plans have been presented by the consultant and permitting is underway.

 

DRAINAGE PROJECTS

  • CR 393 Drainage Improvements- The construction contract has been awarded and project completion is anticipated prior to spring break 2017.
  • Hewett Bayou Watershed- The construction contract has been awarded and project completion is anticipated late summer 2017.
  • Apple Court- In house crews are currently working on this project.  Construction completion is anticipated April 2017.
  • Carlos Court- design has been completed and permits have been issued. Easements have been obtained.  Construction is anticipated to start mid-summer 2017.
  • Spotted Dolphin-design has been completed and permits have been issued. Project has been scheduled to begin early fall 2017.
  • Lakewood Drive-design has been completed and permits have been issued. Project has been scheduled.
  • Brown Street-staff is working on resolving right of way issues.
  • Driftwood Drainage Retrofit Phase I-attempt to satisfy nuisance drainage in phases. In-house drainage crews will replace existing ditches with shallow swales and piping
  • West Mitchell- installation of drainage culvert/pipe. Materials have been ordered and work has been scheduled for spring 2017.

Restore Projects

  • Mack Bayou Drainage Improvements- 60% plans have been submitted and permitting has begun.
  • Western Lake Drainage Improvements-60% plans have been submitted and permitting has begun.
  • Allen Loop Road Drainage Improvements-60% plans have been submitted and permitting has begun.
  • Golf Club Drive Improvements-60% plans have been submitted and permitting has begun.
  • Seagrove Stormwater Improvements-scope has changed due to 395 intersection drainage & Beachside Condos Drainage. Under Design

MISC.

  • Coyote East Landfill- Task 1 conceptual Engineering plans completed. Task II has been issued and work is scheduled to begin this week.